From application to decision: the licensing timeline

How long a premises licence application takes, from the 28 days for comments to the hearing deadline, and when a supplier should make contact.

Published

A new premises licence, or a full variation of one, follows a timetable set by the Licensing Act 2003 and its regulations. Knowing it tells you how long you have before a venue can trade under its licence.

StageHow longWhat happens
ApplicationDay 0The applicant sends the application to the council and must advertise it
Representations28 consecutive days, starting the day after the council receives the applicationThe police, other authorities and residents can comment
No representationsAt the end of the 28 daysThe council must grant the licence as applied for, with the conditions the law requires
Representations madeA hearing must begin within 20 working days of the end of the 28 daysThe council hears both sides, unless everyone agrees a hearing is unnecessary

When to make contact

The application is the earliest public sign, and the 28 days are when an operator is still planning. A venue with no objections can hold its licence about a month after applying. One that goes to a hearing waits longer: 28 days plus up to 20 working days is about eight weeks before the hearing begins.

A licence is not an opening date. Fit-out, staff and stock come before the doors open, which is why the application, not the opening, is the moment to introduce yourself.

Sources

  1. Licensing Act 2003, section 18 (determination of application for premises licence)
  2. Licensing Act 2003 (Premises licences and club premises certificates) Regulations 2005, regulation 22 (as made)
  3. Licensing Act 2003 (Hearings) Regulations 2005, Schedule 1 (as made)